Pool Planning Checklist

Your Complete Dubai Villa Pool Installation Guide
Bookmark this comprehensive checklist to ensure your pool project runs smoothly from planning to completion
PRE-PLANNING PHASE (2-3 months before construction)
❏ Initial Budget Planning
- Set realistic budget range: AED 60,000 - 300,000+ depending on size/features
- Factor in additional costs: permits (AED 10-20k), cooling systems (AED 15-20k)
- Reserve 10-15% contingency fund for unexpected site conditions
- Consider long-term costs: maintenance (AED 500-1,000/month), utilities
❏ Site Assessment
- Measure available garden space and identify optimal pool location
- Check for underground utilities (water, electricity, internet cables)
- Assess machinery access - can excavators reach the planned location?
- Consider sun exposure patterns and privacy from neighbours
- Evaluate drainage and water table conditions
❏ Design Considerations
- Pool Size: Popular Dubai sizes: 6x4m, 8x4m, 9x5m
- Pool Type: Concrete (max customisation), Fiberglass (faster install), Vinyl (budget option)
- Depth Requirements: Standard 1.0m shallow, 1.4-1.5m deep end
- Special Features: Infinity edge (+20-50% cost), water features, integrated spa
- Pool Decking: Marble, natural stone, anti-slip materials

CONTRACTOR SELECTION PHASE
❏ Research Verified Contractors
- Check Trusty Verified Experts: Pools by Design, Secret Gardens
- Verify Dubai Municipality approval and licensing
- Request portfolio of recent Dubai villa projects
- Check customer reviews and references from actual clients
❏ Get Multiple Quotes
- Obtain 3-4 detailed quotes for comparison
- Ensure quotes include: excavation, materials, labour, permits, basic equipment
- Ask about timeline estimates (typically 4-6 weeks for standard pools)
- Clarify what's NOT included: landscaping, advanced lighting, premium finishes
❏ Contractor Evaluation Checklist
- Experience: Minimum 5+ years in Dubai market
- Permits: Will they handle Dubai Municipality applications?
- Communication: Responsive, patient with questions, clear explanations
- Aftercare: Ongoing support after completion
- Insurance: Comprehensive liability and worker coverage

PERMIT & APPROVAL PHASE
❏ Dubai Municipality Requirements
- Submit architectural drawings and pool specifications
- Pay consultant fees (~AED 6,000) and security deposit (~AED 5,000)
- Allow 2-4 weeks for the approval process
- Ensure contractor handles all permit coordination
❏ Community Approvals (if applicable)
- Check homeowners' association rules for pool installations
- Verify any restrictions on pool size, equipment placement, or noise
- Obtain any required community approvals before construction
- Confirm compliance with building setback requirements

CONSTRUCTION PLANNING
❏ Optimal Timing
- Best months: November - March (cooler weather for construction)
- Summer planning: Use hot months for design/permit phases
- Take into Ramadan and mid-summer constraints: Construction may be limited/take longer due to reduced working hours
- Consider travel: Plan around family holidays/travel periods
❏ Pre-Construction Preparation
- Clear and protect existing landscaping that will remain
- Arrange temporary storage for garden furniture/equipment
- Notify neighbours about upcoming construction activity
- Ensure clear access route for construction vehicles and materials
- Set up temporary barriers if children/pets need pool area protection
❏ During Construction
- Regular progress check-ins with contractor (weekly minimum)
- Document progress with photos for insurance/warranty purposes
- Address any concerns immediately rather than waiting
- Verify quality of materials upon delivery
- Maintain clear communication channels with the project manager
CLIMATE CONTROL SYSTEMS
❏ Cooling System (Essential for Dubai)
- Heat Pump Chiller: AED 15,000 - 20,000 for dual heating/cooling
- Capacity Sizing: Professional calculation based on pool volume
- Energy Efficiency: Look for high COP (Coefficient of Performance) ratings
- Installation Planning: Ensure adequate space and ventilation for equipment
❏ Heating Considerations
- Winter Months: December-February may require heating for comfort
- Running Costs: Budget AED 6-8/hour for heat pump operation
- Thermal Covers: Consider covers to reduce heat loss (30-50% savings)
- Smart Controls: Programmable thermostats for automatic temperature management

MAINTENANCE PLANNING
❏ Equipment Selection
- Filtration System: Sand vs cartridge filters - discuss with contractor
- Circulation Pump: Variable speed pumps for energy efficiency
- Cleaning Equipment: Robotic cleaners, skimmers, brushes, vacuum systems
- Water Testing: Digital testing kits vs test strips
- Chemical Storage: Secure, ventilated storage area for pool chemicals
❏ Service Decisions
- Professional Service: AED 400-600/month for weekly maintenance
- DIY Maintenance: Chemical supplies budget ~AED 200-400/month
- Seasonal Adjustments: Increased service frequency during summer months
- Emergency Support: 24/7 contractor availability for equipment failures
💰 BUDGET BREAKDOWN CALCULATOR
❏ Base Pool Costs
- Small Pool (6x4m): AED 60,000 - 120,000
- Medium Pool (8x4m): AED 100,000 - 180,000
- Large Pool (9x5m+): AED 150,000 - 300,000+
- Infinity Edge: +20-50% of base cost
- Premium Finishes: +AED 15,000 - 50,000
❏ Essential Add-Ons
- Permits & Approvals: AED 10,000 - 20,000
- Cooling/Heating System: AED 15,000 - 20,000
- Pool Decking: AED 200 - 800 per m²
- Lighting Package: AED 3,000 - 15,000
- Water Features: AED 5,000 - 25,000
❏ Ongoing Costs (Annual)
- Professional Maintenance: AED 6,000 - 12,000
- Electricity (pumps/cooling): AED 2,400 - 4,800
- Chemicals/Supplies: AED 1,200 - 2,400
- Equipment Repairs: AED 1,000 - 3,000
- Insurance Addition: AED 1,800 - 2,400

🛡️ SAFETY & INSURANCE
❏ Safety Considerations
- Pool Fencing: Removable mesh (~AED 4,000) vs automatic covers (~AED 25,000)
- Non-Slip Surfaces: Essential for pool decking and steps
- Emergency Equipment: Pool alarms, rescue equipment, first aid kit
- Lighting: Adequate underwater and deck lighting for evening use
❏ Insurance Updates
- Notify Insurer: Add pool to home insurance policy
- Liability Coverage: Ensure adequate coverage for guest accidents
- Equipment Coverage: Include pool equipment in policy
- Additional Premium: Budget ~AED 150-200/month for pool coverage
FINAL CHECKLIST BEFORE SIGNING
❏ Contract Review
- Detailed Scope: Every aspect of work is clearly defined
- Timeline: Realistic completion date with weather allowances
- Payment Schedule: Never pay large amounts upfront
- Warranty Terms: Equipment and workmanship warranties are clearly stated
- Change Order Process: How additional work/costs will be handled
❏ Quality Assurance
- Material Specifications: Brand names and quality grades confirmed
- Inspection Schedule: Regular quality checkpoints throughout construction
- Completion Standards: Clear definition of project completion
- Handover Process: Training on equipment operation and maintenance
READY TO START YOUR POOL PROJECT?
Connect with Verified Dubai Pool Experts:
Check Trusty connects you with verified pool installation professionals who understand Dubai's unique requirements:
🏊♂️ Pools by Design - Highly rated with 38+ Google reviews "Lewis and the team have really always taken care of me and been efficient with their process" - Marcus Buchanan
🌿 Secret Gardens - 5.0 rating with comprehensive garden integration, “Secret Gardens was amazing all the way through. On time, great communication, and extremely good quality. If you want a high-end bespoke product, then Secret Gardens are the best.” - Ben, Jumeirah Golf Estates
🍃 Exterior Space Landscape Works - 5.0 rating Elite Expert, “They built a beautiful overflow swimming pool and a BBQ area with a pergola. The quality and finishes are exactly as we saw in the design.” - Amer, The Meadows
Why Choose Check Trusty Verified Experts?
✅ Pre-vetted contractors with proven Dubai experience
✅ Real customer reviews from verified villa owners
✅ Comprehensive service from permits to completion
✅ Local expertise in Dubai's climate and regulations
✅ Ongoing support for maintenance and questions
Bookmark This Checklist & Get Started Today
Save this comprehensive guide and use it throughout your pool planning journey. Each checked box brings you closer to enjoying your dream Dubai villa pool.
Next Steps:
- Complete the Pre-Planning Phase checklist
- Contact Check Trusty verified experts for quotes
- Use this guide during contractor meetings
- Keep this checklist handy throughout construction
Your perfect Dubai pool awaits - let's make it happen!